Sunday 24 November 2024
Select a region
News

Maufant and St. Peter among first in line to get huge buried sewage tanks

Maufant and St. Peter among first in line to get huge buried sewage tanks

Thursday 29 June 2023

Maufant and St. Peter among first in line to get huge buried sewage tanks

Thursday 29 June 2023


Maufant and St. Peter will be among the first places in the island to receive large underground tanks able to store up to 8,000m³ of sewage to allow more houses to be built, the Infrastructure Minister has said.

Deputy Tom Binet explained that both have been identified as centres of population growth because of the development of affordable houses sites, which include two fields in St. Martin and five close to St. Peter’s Village.

Four of those western fields were rezoned in last year’s Bridging Island Plan because of late backbench amendments, and it has subsequently been discovered that the drains there cannot cope with the potential 179 houses that could be built there.

Speaking to Scrutiny this week, Deputy Binet added that Maufant and Five Oaks were also priorities for drainage upgrades because of plans to develop St Saviour’s Hospital for housing and the building of a ‘health village’ opposite – which is a key part of the Government’s ‘New Healthcare Facilities’ programme.

The Infrastructure and Environment (I&E) department recently published a ‘Bridging Liquid Waste Strategy’, which proposes spending £40m over the next four years to avoid ‘catastrophic failures’ in the drainage network.

Part of the solution set out in the strategy is to bury ‘attenuation tanks’ to store sewage to then be released at night back into the network for processing at the new £90m sewage treatment works at Bellozanne, which should be fully operational by the end of this year.

Each circular tank would be a quarter of the size of the Snow Hill cavern, 20m deep and up to 30m wide, although it could be that smaller tanks are used together.

Cavern_pic.jpg

Pictured: The Snow Hill cavern is 80 metres long.

These storage tanks are also likely to be dug at Les Quennevais and in the north of the island, although their exact locations are yet to determined.

The strategy states: “Preliminary investigations by I&E to consider the impact of future large developments suggest that large storage tanks will be required and the cost of these will be several million pounds.

“It is unlikely that such costs can reasonably be fully passed to the developer, particularly where the development is intended to directly meet the Island Plan’s policies and the level of contribution will have to be considered on a case-by-case basis.”

Asked if developers should pay to connect their buildings to the mains network, Deputy Binet replied: “It is arguable that there should be a contribution but what you can’t have is a situation where new developments are paying for the underinvestment level that affects the whole island. 

St Peter fields Bridging Island Plan.png

Pictured: Rezoned fields in St. Peter include two behind Manor Farm.

“In terms of introducing a [liquid] waste charge, that should be across the piece to reflect the level of underinvestment and the amount of money that is needed to keep it up to spec so we don’t find ourselves in this awkward position again.”

The Deputy said that the £40m funding bid, which he said he was confident the Treasury would allocate to his department in the forthcoming Government Plan, was the result of decades of underinvestment by previous administrations. 

Deputy Binet also told the panel that it was “inevitable” that the island’s separate liquid waste and drinking water systems – currently run by the Government and Jersey Water respectively – would be combined in the future to improve efficiency and cost effectiveness.

Addressing the same Environment, Housing and Infrastructure Scrutiny Panel earlier in the day, Treasury Minister Ian Gorst said that the £40m funding bid was still being assessed, although he added that the Council of Ministers had made housing a priority.

“If we consider the cost of housing and supply of housing to be an economic threat, and I do, then we need to deal with this issue,” he said.

However, Deputy Gorst added that he could not recall the drainage network being raised as a major issue when funding for the sewage treatment works was approved in 2014.

“Since then, we have spent nearly £90m on the new sewage works; that was the priority,” he said. “Now, the focus has turned to the network itself. 

“It is never a surprise when a department comes asking for money, but I don’t recall when we supported the treatment works that it was suggested that we would need to spend additional monies as well.”

Pictured top: The Snow Hill Cavern, which is 25,000m³.

READ MORE ...

Plan for 'mini-caverns' around island to unblock drainage pinch points

Sign up to newsletter

 

Comments

Comments on this story express the views of the commentator only, not Bailiwick Publishing. We are unable to guarantee the accuracy of any of those comments.

You have landed on the Bailiwick Express website, however it appears you are based in . Would you like to stay on the site, or visit the site?